In the Works

Published on June 16, 2023

Photo of the Foxton Pools Upgrade from June 2023.

We are making great strides on the Foxton Pools project. Both ends of the building have been demolished and the framing of the enhanced staffroom and storage area has been completed. Our newly revamped reception area has been skilfully framed on its expanded footprint. 

The much-anticipated spa pool is also starting to take shape with foundations and water connections being completed.

Photo of the Tararua Road new sewer pipeline for the Tara-Ika development.

To ensure there is sufficient capacity for future growth, a new sewer pipeline is being installed on Tararua Road, Levin as part of the Tara-Ika development.

Work is progressing well and we appreciate your patience while this work is undertaken. It is expected that the work will be finished by the end of August 2023.